Village Hopes to Complete Parking Lot Before Libertyville Days
The west parking lot behind the rear of businesses on Milwaukee Avenue and the Village Hall still needs landscaping, other work.
Since October 2011, the parking lot behind Libertyville Libertyville Village Hall and west of Milwaukee Avenue has been open to the public, but some work still remains.
“We still need to put the final lift of asphalt down, which is about 1.5 to 2 inches, Dumpster enclosures, landscaping, sidewalk and lighting in the corner near Tommy’s Pizza and 545, laying concrete in that area and striping again,” said Public Works Director John Heinz.
Find out what's happening in Libertyvillewith free, real-time updates from Patch.
Village workers are waiting for asphalt plants to reopen before resuming work on the parking lot.
“When the West Parking Lot is complete is weather-dependent,” Heinz said. “Ideally I’d like to have it done by Libertyville Days, so it’s not hampering the event.”
Find out what's happening in Libertyvillewith free, real-time updates from Patch.
For more about the west parking lot project read:
- West Parking Lot Open to Public, Some Work Remains
- West Parking Lot Substantially Completed by October
- Village Approves $14,000 Change Order for West Parking Lot Project
- West Parking Lot Project Moves Ahead in Libertyville
- West Parking Lot Soil Contaminated with Gasoline
- Village Awards $481,800 Contract to A-Lamp Concrete Contractors
- Village Awards $427,000 Contract to Aldridge Electric